CMU Block & Accessories Calculator

Estimate concrete masonry units and the accessories that go with them from your wall dimensions. Every assumption is shown and adjustable, so you can match it to your own standards.

Wall

Openings

Grout & reinforcing

AssumptionsAdjust to your standards

Typical industry figures. Change them to match how your company estimates.

Fully grouted rate used for 8 in block: 0.26 CY per 100 SF. Units per SF: 1.125.

Total CMU units

1,120

947 SF net wall (1,000 SF gross, 53 SF openings), 15 courses, 5% waste

Get these results as a PDF

We'll email you the full breakdown with your inputs.

We'll use your email to send these results. No spam, and we never share it.

ItemQuantityUnit
Standard blocks8 in x 8 x 16997ea
Corner / end blocks32ea
Bond beam blocks79ea
Lintel blocks12ea
Mortar3 bags / 100 units34bags
Grout0.83CY
Vertical rebar #5456 LF, 476 lb2320 ft bars
Bond beam rebar #4220 LF, 147 lb1120 ft bars
Joint reinforcement770 LF, every 2nd course7710 ft pcs

Need the full masonry takeoff?

We measure every wall type, opening and bond beam from your drawings and price it. Fixed-fee quote within hours.

Upload Plans for a Free Quote

How to use it

  1. 1

    Enter the total wall length and the wall height in feet, and the number of corners and wall ends.

  2. 2

    Pick the block width and add any door and window openings with their sizes and quantities.

  3. 3

    Choose the grout pattern, bond beam courses, and the vertical bar spacing and sizes from the structural drawings.

  4. 4

    Open Assumptions to adjust waste, mortar and grout rates to your company standards.

  5. 5

    Read the quantities off the results table, or upload your plans for a full masonry takeoff.

How the numbers are calculated

Block count
A standard CMU has a nominal 8 x 16 in face, so one unit covers 0.889 SF and a wall takes 1.125 units per SF (112.5 per 100 SF). Net wall area is length x height minus openings.
Courses
Courses are wall height in inches divided by 8, rounded up. Corner and end units are counted as one per course at each corner or end.
Bond beams and lintels
Each bond beam course uses one bond beam unit per 16 in of wall length. Lintels span the opening width plus 8 in of bearing on each side, at one lintel unit per 16 in.
Grout
Grout is the fully grouted rate for the block width per 100 SF, scaled by the share of cells filled. Cells sit 8 in on center, so grouting every 32 in fills one cell in four. Bond beam courses are added as fully grouted strips.
Mortar
Mortar is calculated as bags per 100 units, a common rule of thumb for masonry cement. Set the rate to match your mix and bag size.
Reinforcing
Vertical bars are placed at the chosen spacing plus one at the wall end, each bar the wall height plus the lap allowance. Bars are rounded up to whole stock lengths. Bond beams carry two bars per course. Horizontal joint reinforcement runs every second course with a 10 percent lap allowance.

Common questions

How many CMU blocks are in a square foot?

A standard block with a nominal 8 x 16 in face covers 0.889 SF, so a wall takes 1.125 blocks per square foot, or 112.5 blocks per 100 SF, before waste.

How many blocks are in a 100 square foot wall?

About 113 standard 8 x 16 in blocks, before openings and waste. With 5 percent waste that is roughly 119 blocks.

Does block width change the block count?

No. 4, 6, 8, 10 and 12 in blocks share the same 8 x 16 in face, so the count per square foot is the same. Width changes the grout volume and the weight.

How much grout does a CMU wall need?

It depends on the block width and how many cells are grouted. A fully grouted 8 in wall takes roughly a quarter of a cubic yard per 100 SF. Partially grouted walls take a share of that based on cell spacing.

How much mortar do I need for 100 blocks?

A common rule of thumb is about 3 bags of masonry cement per 100 blocks. Actual use depends on the mix, joint size and crew, so the calculator lets you set your own rate.

Are the results accurate enough to bid?

They are a fast check and a starting point. A bid-ready masonry estimate is measured from the drawings, with wall types, heights, openings, control joints and reinforcing per the structural notes. Upload your plans if you want that done.